Sunday 23 March 2008

Snow and drain.





The sewer is now mostly installed, around the west and north sides of the steading, along with some perforated pipe for surface drainage. Some pics of the inside of the shell too.

Most of the standing water has drained away, following a bit of judicious digging under the wall where the orange poo pipe can be seen on the right. That was a nice job, lying in water digging under the massive stones of a 2 foot thick wall. Look on the bright side though, at least the poo pipe hasn't been used yet.